Crew Discussions
1. What’s STKY on this jobsite?
2. When a STKY event happens, what will protect you/the crew?
3. Is that enough or do you need more?

01 /
  • 01/17/25 – Wind South

    Foundations Excavated – 423/63%

    Foundation Pours Complete – 324/48%

    Foundations Backfilled – 310/46%

    Turbines Delivered – 211 – 31%

    Turbines Erected – 60/90%

    Underground Collection System Installed – 855,060LF/ 31%

    Overhead Collection Structure Install 273/26%

    Substation Completion (7 total) – 57%

  • 01/17/25 – Wind North

    Foundations Excavated – 166/69%

    Foundations Poured – 137/57%

    Foundations Backfilled – 127/52%

    UG Collection Systems Installed – 241,533 LF/21%

    OH Collection Structures Installed – 38/6%

  • 12/31/25 – T-Line

    Foundations Complete – 100%

    Anchors Installed – 100%

    Structures Assembled – 80%

    Structures Erected – 76%

    Conductor Stringing – 33%

  • 12/31/25 – HVDC East

    HVDC Foundations – 620/89%

    Cable Trenching System Installed – 1619 LF/47%

    AC Chopper Foundations – 182/82%

    Yard Steel Erection – 207/40%

    12/31/25 – HVDC West

    HVDC Foundations 657/89%

    Cable Trenching System Installed – 2948/87%

    Yard Steel Erection – 212/41%