01/17/25 – Wind South
Foundations Excavated – 423/63%
Foundation Pours Complete – 324/48%
Foundations Backfilled – 310/46%
Turbines Delivered – 211 – 31%
Turbines Erected – 60/90%
Underground Collection System Installed – 855,060LF/ 31%
Overhead Collection Structure Install 273/26%
Substation Completion (7 total) – 57%
-
01/17/25 – Wind North
Foundations Excavated – 166/69%
Foundations Poured – 137/57%
Foundations Backfilled – 127/52%
UG Collection Systems Installed – 241,533 LF/21%
OH Collection Structures Installed – 38/6%
-
12/31/25 – T-Line
Foundations Complete – 100%
Anchors Installed – 100%
Structures Assembled – 80%
Structures Erected – 76%
Conductor Stringing – 33%
-
12/31/25 – HVDC East
HVDC Foundations – 620/89%
Cable Trenching System Installed – 1619 LF/47%
AC Chopper Foundations – 182/82%
Yard Steel Erection – 207/40%
12/31/25 – HVDC West
HVDC Foundations 657/89%
Cable Trenching System Installed – 2948/87%
Yard Steel Erection – 212/41%