10/9/24 – Wind & Switchyard
984K Manhours Worked
231 Foundations (25% Completed)
123,700 Cubic Yards of Concrete Placed
110 Miles of Underground Collection System Completed
39 GE Turbines Delivered to Site (4% Completed)
104 Overhead Collection Structures Assembled (10% Complete)
101 Structures Assembled on Gen-Tie T-Line (110% Completed)
82% of Electrical Cabling Installed at AC Switchyard
-
10/9/24 – HDVC Transmission Line
1.9M Man hours Worked
880 Miles of Access Road (100% Completed)
2,114 Foundations (99% Completed)
33,000 Cubic Yards of Concrete Placed
5,272 Anchors (100% Completed)
860 Structures Assembled (40% Completed)
1,013 Structure Erected (47% Completed)
76 Miles of Conductor (14% Completed)
-
10/9/24 – HVDC VSC Stations
327K Man hours Worked
987 Foundations (56% Completed)
23,091 CY of Concreted Placed (55% Completed)
80% of Converter Pad Graded & Graveled
14% of Below Grade Work Completed
42% of Structure Steel, Paneling and Roof Sheeting Completed
-
7/12/24 – AC Switchyard Milestones
79 Foundations Installed
6 Breakers Installed (55% Complete)
11 Switches Installed (46% Complete)
Control & Battery Enclosures Delivered & Installed
Buss & Control Wiring Underway