Scroll Down
Top Stories
Stay informed with what’s happening across the SunZia Project.

Subscribe to Crew Channel stories
Have a Story Idea for Crew Channel?

Safety Topics of the Week

Give Large Vehicles the Right-of-Way
They have limited visibility and require longer stopping distance.

Walk-Around Inspections
Before operating any equipment, conduct a thorough walk-around to spot leaks, damage, or potential hazards.

Close Gates
Prevent livestock from escaping, reduce the risk of disease spread, and protect the landowner’s investment.

PPE Inspections
Inspect all PPE daily to ensure its free of damage and in proper working condition.


01 /
  • 7/11/25 – Wind South

    Foundations Excavated – 633/94%

    Foundation Pours Complete – 564/84%

    Foundations Backfilled – 557/83%

    Turbines Delivered – 454/67%

    Turbines Erected – 220/33%

    Underground Collection System Installed – 1,817,723 LF / 64%

    Overhead Collection Structure Install 558/54%

    Substation Completion (7 total) – 82%

  • 1/17/25 – Wind North

    Foundations Excavated – 166/69%

    Foundations Poured – 137/57%

    Foundations Backfilled – 127/52%

    UG Collection Systems Installed – 241,533 LF/21%

    OH Collection Structures Installed – 38/6%

  • 6/30/25 – T-Line

    Foundations Complete – 100%

    Anchors Installed – 100%

    Structures Assembled – 100%

    Structures Erected – 100%

    Conductor Stringing – 100%

  • 7/14/25 – HVDC East

    HVDC Foundations – 695/100%

    Cable Trenching System Installed – 3462/100%

    AC Chopper Foundations – 223/100%

    Yard Steel Erection – 468/97%

    7/14/25 – HVDC West

    HVDC Foundations 740/100%

    Cable Trenching System Installed – 3408/100%

    Yard Steel Erection – 512/100%