Stay informed with what’s happening across the SunZia Project.

Subscribe to Crew Channel stories
Have a Story Idea for Crew Channel?

Different Name, Same Concept

“It’s about seeing safety as a presence of defenses rather than an absence of recordable incidents.”

Pattern Energy’s Senior Director of Health and Safety Ben MacDonald.

Crew Discussions
1. What’s STKY on this jobsite?
2. When a STKY event happens, what will protect you/the crew?
3. Is that enough or do you need more?

01 /
  • 10/9/24 – Wind & Switchyard

    984K Manhours Worked

    231 Foundations (25% Completed)

    123,700 Cubic Yards of Concrete Placed

    110 Miles of Underground Collection System Completed

    39 GE Turbines Delivered to Site (4% Completed)

    104 Overhead Collection Structures Assembled (10% Complete)

    101 Structures Assembled on Gen-Tie T-Line (110% Completed)

    82% of Electrical Cabling Installed at AC Switchyard

  • 10/9/24 – HDVC Transmission Line

    1.9M Man hours Worked

    880 Miles of Access Road (100% Completed)

    2,114 Foundations (99% Completed)

    33,000 Cubic Yards of Concrete Placed

    5,272 Anchors (100% Completed)

    860 Structures Assembled (40% Completed)

    1,013 Structure Erected (47% Completed)

    76 Miles of Conductor (14% Completed)

  • 10/9/24 – HVDC VSC Stations

    327K Man hours Worked

    987 Foundations (56% Completed)

    23,091 CY of Concreted Placed (55% Completed)

    80% of Converter Pad Graded & Graveled

    14% of Below Grade Work Completed

    42% of Structure Steel, Paneling and Roof Sheeting Completed

  • 7/12/24 – AC Switchyard Milestones

    79 Foundations Installed

    6 Breakers Installed (55% Complete)

    11 Switches Installed (46% Complete)

    Control & Battery Enclosures Delivered & Installed

    Buss & Control Wiring Underway